Here's a list of some of the things to be done:
- Installation of a new 20-core server to host SHA-256 daemons for mining
- Upgrade of the database to Postgres 10, which features additional parallelism
- Copying and relocation of virtual machines
- Assembly and installation of a floor-to-ceiling server rack to replace the makeshift platforms
- Running of a 240V 50A power line to the server area for future capacity
- Installation of a return duct to vent waste heat
- Addition of a large uninterruptable power supply to provide enough power until generator startup
- Switchover to a direct enterprise-class Internet connection that protects against DDoS attacks, replacing our VPN workaround
- Upgrade of the 2014 original server to add additional cores
- Installation of more solid state disks on all servers to handle expanding blockchains, especially Ethereum's massive blocks
Since all services will be offline as the Internet connections are reconfigured, these forums will also be unavailable and updates will be provided on twitter.
Weather forecasts currently indicate that the polar vortex may result in a Nor'easter bringing snow just before Thanksgiving. If a blizzard occurs, this maintenance will be rescheduled.